Bond Construction/Completion Timeline

 CLICK ON LINKS TO THE LEFT, UNDER HEADLINES TO NAVIGATE TO BOND TOPICS

April 2015--August 2017 Master Planning

October 2016--August 2017  Building Committee Meetings

August 2017--DISD Board of Trustees Call Bond

September 2017--November 2017  Bond Information Program

November 7, 2017--Bond Election

November 2017--April 2018  Schematic Designs, Design Development, and Construction Documents

May 2018--Proposals/Bids

June 2018--Contractor Contract

July 2018--August 2019  Construction Phase

 